Internal Audit Key Compliance Attributes – Update on Key Compliance Attribute 3 (November 2025)

Departments with internal audit functions are required to publish key attributes of compliance as per section A.2.2.3 of the Treasury Board Directive on Internal Audit. This requirement includes a mid-year update on the implementation of the risk-based audit plan, including Management Action Plans (MAP). Please note that only planned and ongoing audit engagements, in addition to completed audit engagements with outstanding MAPsFootnote 1, are included in the tables below.

Risk Based Audit Plan and related information – updated as at November 30th , 2025.

2017-18 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of repayable contributions

Published:

MAP not fully

implemented

2018/10/31

2019/02/27

2019/12/31

80%

2018-19 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Common Services Delivery Points

Published:

MAP fully

implemented

2019/08/21

2019/12/19

2020/03/01

100%

2019-20 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Foreign Service Directive 15 - Relocation

Published:

MAP not fully

implemented

2021/01/25

2021/04/26

2021/12/31

90%

2020-21 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Real Property - Strategic Portfolio and Investment Planning

Published:

MAP fully

implemented

2021/11/09

2022/02/11

2023/06/31

100%

2021-22 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of IT Application Portfolio Management

Published:

MAP fully

implemented

2022/12/16

2023/04/06

2024/09/31

100%

2022-23 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Management Practices of Mission - Dakar

Published: MAP fully implemented

2023/11/28

2024/01/23

2024/03/31

100%

2023-24 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Procurement of Consulting Services

Published:  MAP fully implemented

2023/12/11

2024/03/28

2024/12/31

100%

Audit of the US Mission Network

Completed:

MAP not fully implemented

2025/12/22

-

2024/12/31

68%

2024-25 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Audit of Management Practices of Missions – Washington

In-progress

N/A

N/A

N/A

N/A

Audit of the Global Arctic Leadership Initiative

Published:

MAP not fully implemented

2025/07/21

2025/09/15

2026/03/31

0%

Audit of the Armoured Vehicle Program

In-progress

N/A

N/A

N/A

N/A

Mission Focused - Real Property, Service Line Projects

In Progress

N/A

N/A

N/A

N/A

Transformation Project: Grants & Contributions Transformation

In-Progress

N/A

N/A

N/A

N/A

2025-26 Risk Based Audit Plan

Internal AuditAudit StatusReport Approved DateReport Published DateOriginal Planned MAP Completion DateImplementation Status

Transformation Project: Global Affairs Canada RenoFootnote 2

In Progress

N/A

N/A

N/A

N/A

Audit of Management Practices at Missions – Nairobi (Follow-Up)

In Progress

N/A

N/A

N/A

N/A

Audit of Deferred Maintenance of GAC Buildings

In Progress

N/A

N/A

N/A

N/A

Audit of Compliance with Housing Policy

Planned

N/A

N/A

N/A

N/A

Audit of CanExport Program (Follow-Up)

Planned

N/A

N/A

N/A

N/A

Audit of Digital Literacy and Security Awareness

Planned

N/A

N/A

N/A

N/A

Audit on the Administration of Foreign Service Directives at Missions

Planned

N/A

N/A

N/A

N/A

Date modified: